The Water & Sewerage Company Inc. (WASCO) early in 2015 had completed the first phase, i.e., The Study, for the John Compton Dam de-Silting and Rehabilitation project. After which, request for proposals (RFP) had been sought from two (2) prequalified firms to undertake the second phase of the project, i.e., The Works. In November 2015 WASCO sought a pre-bid meeting with the pre-qualified firms and the deadline for the submission of proposals from them, was December 2015. This process reached the negotiations stage but failed as the bidder was unwilling to meaningfully negotiate. The process was subsequently terminated and a new process ensued thereafter.
The Senior Manager Operations, Aly Anthony noted, “the John Compton Dam rehabilitation project is essentially a dredging and disposal project including a Catchment Rehabilitation component to reduce on the impact of landslides and other mass earth movements in the reservoir.”
The project, funded by Caribbean Development Bank (CDB) with financial assistance from the European Investment Bank and the Inter American Development Bank is being undertaken by Water & Sewerage Company Inc. (WASCO), and is set up to ensure accountability and transparency where the CDB is involved in every significant stage of the project and has to give its ‘No objection’ before WASCO can move to another stage. The Central Tenders Board too also has to provide its ‘No Objection’.
The selected evaluation committee consists of WASCO in-house staff, members of the Board of Directors and at least one suitable person from another government agency. The CDB and the CTB has to first approve the evaluation committee
The typical procurement process used was as follows:
The tender documents were revised and advertised but instead of a prequalification process, a post-qualification process was undertaken. This process will shorten the procurement process as once the bidder does not fully comply with the post-qualification criteria, the bid will be rejected. The process as outlined in the CDB procurement rules will continue until a successful bidder emerge. An evaluation report will be generated and submitted to the CDB and CTB for their ‘No Objection” to enter into negotiation with the most successfully bidder first. If negotiations succeed then the bidder is awarded the contract.
A Project Management Unit was developed to manage this project. This unit is currently being headed by a senior engineer from Trinidad. The unit will be staffed by two Project Engineers, an Environmental Monitoring Officer and a cadre of support staff.
Currently, the Request for Proposals for the John Compton Dam Rehabilitation project has been advertised and proposals are expected to be received by the CTB on 23rd September 2016 with an anticipated public opening shortly thereafter. Evaluations will be undertaken by the evaluation committee and submitted to the CDB and CTB for their ‘No Objection’ to enter into negotiations with the successful post-qualified bidder or bidders. If all goes well, a contract is expected to be awarded before end of year 2016.
The other key components of the project are as follows:
The entire process has been carried out in keeping with the Caribbean Development Bank (CDB) procurement rules which require 'no objections' from the CDB before proceeding from one stage to the next. It also requires all submissions to be received and opened by the Central Tenders Board and the approval of that Board to undertake the stages. WASCO has satisfied all the requirements of the CDB rules and the Central Tenders Board, and therefore has progressed the project to the current Works Phase.
Hence, the Water and Sewerage Company Inc wishes to clarify that;